Works resume on Second Range Crossing after safety report

WORK has resumed on the largest bridge under construction on the Toowoomba Second Range Crossing.

Transport and Main Roads Director General Neil Scales said the stop-work order was lifted at 5pm today after contractor Nexus provided a detailed plan for managing the health and safety of workers working on elevated structures.

The order was made for a period of seven days starting May 1, but the department extending it due to not being satisfied at the measures taken by the contractor.

"The Department ordered work to stop on the viaduct because we felt safety practices on site were not being properly followed, putting workers at risk," Mr Scales said.

"Over the past few weeks, Nexus has put measures in place to prevent future incidents around working at height, outlined in an improved safety plan.

"We have reviewed that revised plan and have been reassured that Nexus has taken the right steps to comprehensively manage health and safety risks at the viaduct."

The State Government suspended work at piers 2 and 3 of the viaduct from 1 May after steel-reinforcing bars fell from a low-height onto a vehicle. There were no injuries.

Mr Scales said the $1.6 billion Toowoomba Second Range Crossing project would deliver national economic benefits through greater freight efficiency and driver safety, and relieve pressure on Toowoomba's roads.

"Despite the reported delay arising from a geotechnical issue that was identified earlier this year, all other works will be completed in line with the original time frame," he said.

"We are starting to see this once-in-a-generation project take shape with traffic travelling on recently opened sections of the crossing."

Earthworks are more than 95 per cent complete, bridges and structures are more than 90 per cent complete and surfacing with foamed bitumen is more than 30 per cent complete.


Winds whip up fires across parts of northern NSW

Winds whip up fires across parts of northern NSW

AVIATION support is assisting at one of four blazes in the Tenterfield Shire.

10 years, $5M, one amazing coastal pathway

Premium Content 10 years, $5M, one amazing coastal pathway

You will not be disappointed by this epic coastal pathway

Ballina women urged to take steps to reduce stress

Premium Content Ballina women urged to take steps to reduce stress

NEW research reveals 95 per cent of Australian women experience stress.