Cougar Energy closer to shipping coal through Gladstone

CONTROVERSIAL Australian Securities Exchange-listed Cougar Energy is one step closer to shipping coal through Gladstone, with the company completing a conceptual longwall study on its Mackenzie PCI Coal Project.

The project, located about 25km north-east of Blackwater, was found to have an inferred resource of 201 million tonnes.

It also completed a capital cost and operating cost breakdown, with any such longwall operation to set Cougar back $860 million.

It also noted that ongoing operating costs would be about $113 per tonne.

Cougar chairman Andrew Matheson said it would now look at funding the project.

The company was recently fined $75,000 by the state government after being found to have released benzene into the local water supply at Kingaroy as a result of its underground coal gasification trial.

However, the department of environment found that there was no actual harm to the environment as a result of the release.


Three times the Elvis appeal

Three times the Elvis appeal

Elvis - An American Trilogy show is coming to the Northern Rivers

Un bon film! French cinema festival is coming

Un bon film! French cinema festival is coming

Alliance Francaise Cote du Nord has unveiled this year's program

A beauty, a beast and some singing cutlery sought

A beauty, a beast and some singing cutlery sought

Ballina Players is auditioning for Beauty and the Beast

Local Partners